Single Crystal Diffractometer (TOPAZ) - Schedule
- Detector Assembly (April/08)
- Instrument Enclosure Construction (May/08)
- Delivery of neutron guide SA#2 & #3 (June/08)
- Installation of neutron guide (July/08)
- Installation of BW Chopper stands and bases (July/08)
- Detector module design finalized and prototype testing begins (November/08)
- Delivery of Sample Positioning System (November/08)
- Instrument hutch and infrastructure installation (November/08)
- Installation of final neutron guide assemblies (December/08)
- Installation of BW Choppers (January/09)
Recent Significant Events
- Poured in place concrete sample cave (September/08)
- Sample Environment design finalized for production (August/08)
- Installation of BW Chopper stands and bases (July/08)
- Installation of vacuum system for evacuated components under shielding (July/08)
- Installation of neutron guide SA#2 & #3 (July/08)
- Delivery of neutron guide SA#4, #5 , and primary optics (July/08)
- Delivery of neutron guide SA#2 & #3 (June/08)
- Installation of neutron guide SA#1 (March/08)
- Delivery of neutron guide SA#1 (Febuary/08)
- Complete design of instrument enclosure shielding (September/07)
- Integrated Design review – Instrument Milestone (June/07)
- Base plates for stacked shielding installed, aligned and grouted (April/07)
- Delivery of neutron guide housing of subassembly SA#1 & SA#2 of 6 (April/07)
- Begin of fabrication of subassembly SA#1 (February/07)
- Bulk shield insert (BSI) shielding filled with heavy concrete and installed (January/07)
- Front End (FE) shielding filled with heavy concrete and installed (January/07)
- Stacked shielding procured and on order (January/07)
- Poured-in-place shielding complete (November/06)
- Neutron Guide contract awarded (August/06)
- Shutter Insert Housing, Collimater Cartridge, Shutter Insert Assembly, and Shutter Gate installed (December/05)
|
|
|
|
|
|